Create a milestone that's due on a fixed date, or one that becomes due when a stage finishes.

Open the project and go to the Milestones tab.

Click Add milestone.

Enter a Milestone name.

Under Remind owner, choose On a date or When a stage completes (explained below), and fill in the fields for that option.

Optionally enter an Amount (AED).

Choose one or more Owners: the people who should chase this milestone. Optionally add a Description.

Save. The milestone appears on the Milestones tab with its due date and reminder status.

Choosing when it's due

Use this when the contract gives a fixed date.

  • Due date: the day it's due.
  • Days before (optional): how many days before the due date reminders should start. Leave it empty to use your organization's default, which is 7 days unless your organization has changed it.

Example: due 30 November, Days before left empty → reminders start on 23 November.

Which should I pick?

If the contract names a date, use On a date. If it says "upon" or "after" something happens, use When a stage completes. Mabny then works out the date for you and nobody has to remember to set it.

Changing a milestone later

Open the ⋯ menu on the milestone and click Edit. A few limits apply:

  • Once a stage-linked milestone's stage has finished, only its due date can change, not which stage it's linked to.
  • A date milestone that has already sent a reminder can't be switched to a stage trigger.
  • Changing the date doesn't restart reminders that were already acknowledged.

Who can do what

  • Any member can add, edit, complete, cancel or delete milestones.
  • Only the milestone's owners or an admin can acknowledge its reminder.
  • Only admins and people whose job role has the View financial values permission can see or set the amount. See Permissions.
  • Milestones can't be added to a completed project.